Intervals between tasks

rpamazz

New Member
Hi!

I have a question connected with blue prism scheduler.

Is it possible to define intervals between tasks?

For instance I want to log into machine using another account exactly 1 minut after logging out. By default logging in shortly after logging out doesn't work - process gets terminated, because machine wants to log in while logging out is still in works.

Also, I want to start process exactly 5 min after previous one. I know I can input 5 min sleep at the end of the process but is there more sophisticated way to do this?

I'm using Blue Prism 6.2.
 

gil.silva

Active Member
Hello rpamazz,

After BP 6.3 you have the option Post Completions Delay, which does exactly what you need, I strongly recommend you to update, since BP is already in the version 6.6 and there's a lot of new features and bugs fixed since 6.2.
 