Hi All,
I have some questions related to Login Agent
So Here is the scenario: if Process A was scheduled at 8: 00 AM it? need to unlock the window for that we need to incorporate the login agent in the same process A which we want to run at 8: 00 AM or do we need to create separate process for that?

If we want to run the Login Agent process separately Do we need to schedule the login Agent Before 8: 00 AM to run the process A?

What would be the best Approaches to do that?>
 

rbhagavathsingh

New Member
Yes give 10 min difference between two processes
If you are using older version then you have to use two schedules
If 6.4+ then you can give a delay between tasks

The 10min is more than sufficient for login agent to login and run the resource PC .

Hope that helps
 